• <tr id='GwhmTi'><strong id='GwhmTi'></strong><small id='GwhmTi'></small><button id='GwhmTi'></button><li id='GwhmTi'><noscript id='GwhmTi'><big id='GwhmTi'></big><dt id='GwhmTi'></dt></noscript></li></tr><ol id='GwhmTi'><option id='GwhmTi'><table id='GwhmTi'><blockquote id='GwhmTi'><tbody id='GwhmTi'></tbody></blockquote></table></option></ol><u id='GwhmTi'></u><kbd id='GwhmTi'><kbd id='GwhmTi'></kbd></kbd>

    <code id='GwhmTi'><strong id='GwhmTi'></strong></code>

    <fieldset id='GwhmTi'></fieldset>
          <span id='GwhmTi'></span>

              <ins id='GwhmTi'></ins>
              <acronym id='GwhmTi'><em id='GwhmTi'></em><td id='GwhmTi'><div id='GwhmTi'></div></td></acronym><address id='GwhmTi'><big id='GwhmTi'><big id='GwhmTi'></big><legend id='GwhmTi'></legend></big></address>

              <i id='GwhmTi'><div id='GwhmTi'><ins id='GwhmTi'></ins></div></i>
              <i id='GwhmTi'></i>
            1. <dl id='GwhmTi'></dl>
              1. <blockquote id='GwhmTi'><q id='GwhmTi'><noscript id='GwhmTi'></noscript><dt id='GwhmTi'></dt></q></blockquote><noframes id='GwhmTi'><i id='GwhmTi'></i>

                您现在的位置是:首页 > 新闻资讯网站首页新闻资讯

                寰球工程公司广东石化化工区雨水收集池底板混凝土浇筑圆满完成

                2月23日凌晨1:06分,经过19个小时╱连续奋战,广东石化化工区雨水收集池最后一块底板混凝土浇筑顺利完成,为该ω 雨水收集池底板混凝土浇筑画上...

                2月23日凌晨1:06分,经过19个小时〗连续奋战,广东石化化工区雨水收集池最后一块底板混凝土浇筑顺利完成,为该雨水收集池底板混凝土浇筑画上了圆◤满的句号。

                图片

                雨水收集※池长454米、宽20米,水⊙池底板采用筏板基础,厚700毫米,混ぷ凝土设计强度等级为C40抗渗等级P10。水池筏板基础结构尺寸体积较大,配筋较密,对质量及防水】要求高。

                为保证项目尽早建成投产,公辅设施(二)分项目部根据项目实际特点,科学组织,分区施工,将雨水收」集池体分为十五块,同时施工单◤数区块,流水施工双数分区。与此同时,春节期间,项目部广大干部员工积极响应公司号召,主动█留守现场,积极组织人员,保证每天施工人数不少于120人,为节日ㄨ期间项目安全平稳、高效推进提供了可靠人力保障。

                施工过程中,项目管理人员驻扎一□ 线,紧盯工程进度,加强过程检查,严把工程◣质量关,做到及时发现问☆题、有效解决问题、杜绝质量¤隐患,做到速度与质量两不误、两促进。

                经过项目部与施工单位、监理等√各方人员的同心协力,截至目前,雨水收♀集池施工进度已达70%,比计划进度超前15个百分点。